Margaret K. Kulpa, Kent A. Johnson

"Interpreting the CMMI: A Process Improvement Approach, Second Edition"


The point to note is that the process areas listed in Level 2 are not listed in Level 3,
and vice versa. The same holds true for Maturity Level 4 and Maturity Level 5. You
must satisfy all of the goals in the previous levels plus the goals for the current level
in order to attain the maturity level rating. Each maturity level consists of process
areas. Each process area contains goals that must be satisfied. Each goal has certain
practices or actions associated with it.
n n n n n n n n
Process Area Maturity Level
(staged representation)
Requirements Management
Project Planning 2
2
Project Monitoring and Control 2
2222
Supplier Agreement Management
Measurement and Analysis
Process and Product Quality Assurance
Configuration Management
Requirements Development
Technical Solution
Product Integration
Verification
Validation
Organizational Process Focus
Organizational Process Definition (with IPPD) 33
3 3 3 3 3 3
Organizational Training
Integrated Project Management (with IPPD) 333
Risk Management
Decision Analysis and Resolution
Organizational Process Performance 4455
Quantitative Project Management
Organizational Innovation and Deployment
Causal Analysis and Resolution
table 4.